How to plan client review moments into a video schedule
Treat every client review as a fixed moment in the schedule: a date the work is sent, a closing time for notes, a named person who must review, and the number of rounds agreed for that stage. Plan the making around those windows, and agree them with the client at kickoff. Review time is part of the timeline, and a schedule that leaves it out is wrong from the first day.
Why do video schedules slip at the review stage?
Because most schedules plan the making in detail and leave the reviewing as empty space.
A typical production schedule shows edit days, animation weeks and grading sessions. Between them sit arrows labeled “client feedback”, with no length and no owner. Those arrows are where the time goes. Decade Pictures gives an example that will be familiar to anyone in post: a first cut delivered on a Monday, watched the same afternoon, then passed around internally until the notes come back a full week later. Their conclusion is blunt: every day a review is late moves the delivery date by a day.
Feel Right, a commercial production company, describes the other side of the same coin in its process guide: notes that arrive bundled from one person keep a job moving, while scattered or contradictory input slows it down, and speed depends as much on decision makers being reachable as on the crew.
Neither problem is solved by working faster. It is solved by giving the review a place in the plan.
What is a review moment?
A planned point where the client judges a specific stage, with a start, an end and an agreed scope.
Each review moment answers five questions:
- What is being judged? Script, storyboard, rough cut, fine cut, grade and mix, or deliverables.
- When is it sent? A date and time, so the reviewer can block time for it.
- When does the window close? A date and time in the client’s time zone.
- Who must review? One person who sends consolidated notes, plus anyone who must see it.
- How many rounds does this stage allow? For example, two rounds on the edit before picture lock.
Written together, they turn “client feedback” into something both sides can plan around. For what counts as a round and how windows define it, see what counts as a revision round.
How long should each review window be?
Long enough for the right people to watch and agree, short enough to keep the team moving. This table is our suggestion for a 30-to-60-second commercial with one decision maker and a few reviewers, not an industry rule.
| Stage | Suggested window | Who must look | Rounds |
|---|---|---|---|
| Script or storyboard | 2 to 3 business days | Decision maker, brand, legal for claims | 1 to 2 |
| Rough cut | 2 to 3 business days | Decision maker and core reviewers | 1 |
| Fine cut | 2 business days | Decision maker and core reviewers | 1 to 2 |
| Picture lock | 1 business day | Decision maker, explicitly | 1 |
| Grade and sound | 1 to 2 business days | Decision maker, brand | 1 |
| Deliverables check | 1 to 2 business days | Channel owners, market leads | 1 |
For comparison, Contentoo’s approval guide recommends a window of 24 or 48 hours for written content. Video usually needs a little more, because a reviewer has to watch, often more than once, and several people have to agree before the notes go out. Add a day for every extra layer between the decision maker and the maker, such as an agency between brand and production company.
How do you build the schedule backwards from the launch?
Start at the launch date, place the review windows first, and fill the making time between them.
Working backwards shows early whether a date is realistic. A simple order:
- Fix the launch or air date, and the date files must reach the media agency or platform.
- Place the deliverables check a few days before that, with time to fix what it finds.
- Place grade and sound review, then picture lock, then the edit rounds, each with its window.
- Fill in the making time between the windows: edit days, animation, grading, mixing.
- Add a buffer before the delivery date, a day or two on a short job, more on a long one.
- Check the result against the shoot or production dates. If it does not fit, cut a round or move the launch now, not in week five.
Here is an illustrative edit and finishing phase for a 30-second film, starting after the shoot:
| Week | Making | Review moment |
|---|---|---|
| 1 | Edit to rough cut | Rough cut sent Thursday, closes Monday 12:00 |
| 2 | Fine cut | Fine cut sent Wednesday, closes Friday 12:00 |
| 3 | Fine cut v2, picture lock | Lock requested Tuesday, closes Wednesday 17:00 |
| 3 to 4 | Grade, mix, graphics | Grade and sound sent Monday, closes Tuesday 17:00 |
| 4 | Deliverables, QC | Deliverables sent Thursday, closes Friday 17:00 |
Note the closing times at noon on some days. A window that closes at noon gives the maker the rest of the day to read the notes and plan, so the next working day starts with action instead of reading.
What do you do when a review moment slips?
Move everything after it by the same amount, and say so the same day.
When notes arrive two days late, the honest response is a new schedule with every later date moved by two days. The tempting response is to absorb it by compressing the maker’s time, which quietly turns a client delay into overtime and lower quality. If the delivery date truly cannot move, offer a choice instead: drop a round, simplify a deliverable, or add people. Make it the client’s decision, in writing.
It also helps to separate a late review from a late reviewer. If the decision maker is away, ask for a named stand-in at kickoff who can approve within the agreed scope. Our guide on getting every stakeholder into round one covers how to name those people before the first cut.
How do you make review moments visible to everyone?
Put them where people already look: their calendar, and the project itself.
Send calendar invites for each review window to the people who must review, with the closing time in the title. Keep the full schedule in one shared place, and update it the moment a date moves. A deliverables list with dates per item, as described in our commercial deliverables list guide, closes the loop at the end.
Some production tools hold the review plan next to the work. Kadrenta, made by the same team behind The Production Brief, keeps a Planning tab under the project’s details for client moments and the agreed revision rounds per moment, and task deadlines can be subscribed to as a calendar feed in Google, Apple or Outlook. A review round and its email can also be scheduled to go out at a set moment, so a cut finished on Friday evening can land with the client at 9:00 on Monday, at the start of the window you agreed.
Frequently asked questions
Who should own the review dates, the client or the production side?
The production side proposes them, the client confirms them at kickoff. After that, both sides treat them like shoot days: moving one is a decision, not a drift.
How many review moments does a 30-second commercial need?
Typically one for script or storyboard, two or three for the edit, one for grade and sound, and one for deliverables. Fewer is possible on simple work; more usually means the brief was unclear.
Should review moments be calendar invites?
Yes, for the people who must review. A calendar block for the review window makes the time visible and protects it from other meetings.
What if the client wants to see work between the planned moments?
Share it as an informal look, clearly labeled, with no round attached. Formal notes still wait for the planned moment, so the extra look does not become an extra round.